Snow, snow, and more snow!

The weather continues to affect the progress of the renovation. Snow removal will be the first order of business this week as steelworkers continue with the detailing and decking of the addition on the east side of the building. Concrete will be poured in the new mechanical room on the lower level and the crane will be moving to the south end of the building to place the columns and running track for the new Open Rec Area. Check out the pictures to see the near two feet of snow blanketing the construction area.